Detail plan of Reinforcement lean concrete, stub column and pile cap.
<p>This Architectural Drawing is AutoCAD 2d drawing of Detail plan of Reinforcement lean concrete, stub column and pile cap. Total Cutting Length for Vertical Reinforcement = Anchorage Length at the bottom of the pile + the height of the pile + development length (40d) + Lap length (50d) – clear cover provided at the bottom. The overall depth of pile cap shall also be selected such that the effective depth of bottom reinforcement is <strong>at least 12 inches</strong>. The grade of concrete to be used for piling should be <strong>minimum M25</strong> (or as as required at the site for load conditions) with the minimum cement content of 400 kg/m<sup>3</sup>. For more details and information download the drawing file.</p>